Past Performance Project Narrative

Solicitation: Vendor Profile                                                                         Project No.: 910-911

Contractor:  Havlovick Engineering Services, Inc. (HES) 

Project/Location:      Firemain Loop for the DD(X) Program, Machinery Space Scenario, ex-USS SHADWELL, Mobile, AL

Client:       Bath Iron Works, Inc. / U.S. Department of Defense

Master Contract #:   PSA No. 7190-0012-A28

Contract Type: Time & Materials

Brief Description of Project:  

The Machinery Space Firepump Compartment was a design and installation of pumps, piping and controls to provide an automated fire suppression system for the DD(X) project.  This project required the following engineering disciplines:  mechanical, fluids, electrical, and instrumentation and controls.

  • The mechanical and fluid components of the system were designed to allow either pump to serve the firemain individually or together as required by the load.

  • Electrical distribution for the facility was modified to accommodate the significant increase in electrical load required by two 460 VAC, 600 AMP pumps.

  • The pumps were automatically controlled by variable frequency drives (VFDs) to maintain a constant pressure in the system.  Pressure setpoints or manual overrides were available locally at the VFDs or in two separate remote locations.  A sleep mode was also integrated into the system to prevent an overpressure situation.

The complete system was also managed and installed by HES personnel, assuring customer satisfaction.

Additional Views

HES POC

 

Mr. Bradley Havlovick
Project Manager
Havlovick Engineering Services, Inc.
290 Chestnut Street

Idaho Falls, ID
83402
Phone: 
208-523-7424
Fax:
208-528-6159
Email: bhavlovick@hes1.com

 